2 Storey Duplex First Billing

🏡 Demolition and Building Construction of 2-Storey Duplex Residential

Client: Rifon N. Quiblat / Evelyn C. Quiblat

Location: Block 9, Lot 5, Gold City Village, Lower Balulang, Cagayan de Oro City

Item No. / Description / Qty / UnitContract Amount (₱)Actual (%) / Billing (%) / Billing Amount (₱)
1.1 Demolition
Qty: 1, Unit: lot
₱380,517.00 Actual: 85.00%
Billing: 6.19%
Billing Amount: ₱323,439.45
1.2 Mobilization
Qty: 1, Unit: lot
₱62,682.67 Actual: 90.00%
Billing: 1.08%
Billing Amount: ₱56,414.40
1.3 Permits and Licenses
Qty: 1, Unit: lot
₱7,835.37 Actual: 100.00%
Billing: 0.15%
Billing Amount: ₱7,835.37
1.4 Site Security and Safety
Qty: 1, Unit: lot
₱5,745.94 Actual: 100.00%
Billing: 0.11%
Billing Amount: ₱5,745.94
1.5 Temporary Facilities
Qty: 1, Unit: lot
₱31,341.49 Actual: 90.00%
Billing: 0.54%
Billing Amount: ₱28,207.34
1.6 Site Clearing and Preparation
Qty: 1, Unit: lot
₱94,024.46 Actual: 70.00%
Billing: 1.26%
Billing Amount: ₱65,817.12
2.1 Excavation and Earthworks
Qty: 34.92, Unit: cum
₱48,522.94 Actual: 75.00%
Billing: 0.70%
Billing Amount: ₱36,392.21
2.2 Site Grading
Qty: 300, Unit: sqm
₱416,863.77 Actual: 70.00%
Billing: 5.59%
Billing Amount: ₱291,804.64
2.3 Excavation for Foundations
Qty: 24.12, Unit: cum
₱33,515.85 Actual: 70.00%
Billing: 0.45%
Billing Amount: ₱23,461.09
2.4 Backfilling and Compaction
Qty: 16.88, Unit: cum
₱23,455.54 Actual: 20.00%
Billing: 0.09%
Billing Amount: ₱4,691.11
3.1 Concrete Footings
Qty: 9.45, Unit: cum
₱203,719.66 Actual: 100.00%
Billing: 3.90%
Billing Amount: ₱203,719.66
3.2 Reinforcement Works
Refer to structural design
₱156,707.43 Actual: 100.00%
Billing: 3.00%
Billing Amount: ₱156,707.43
4.1 Concrete Columns, Tie Beams, Slab, Stairs
Based on components
₱540,912.26 Actual: 65.00%
Billing: 6.73%
Billing Amount: ₱351,592.97
4.2 Form Works (Columns, Beams, Slab, Stairs)
Based on structural area
₱169,035.08 Actual: 100.00%
Billing: 3.24%
Billing Amount: ₱169,035.08
5.1 Scaffolding Works (Columns)
Refer to lumber requirements
₱52,235.81 Actual: 100.00%
Billing: 1.00%
Billing Amount: ₱52,235.81
5.2 Scaffolding Works (Beams)
Refer to lumber requirements
₱25,595.55 Actual: 100.00%
Billing: 0.49%
Billing Amount: ₱25,595.55
5.3 Scaffolding Works (Slab)
Refer to lumber requirements
₱26,640.26 Actual: 100.00%
Billing: 0.51%
Billing Amount: ₱26,640.26
5.4 Scaffolding Works (Stairs)
Refer to lumber requirements
₱52,235.81 Actual: 100.00%
Billing: 1.00%
Billing Amount: ₱52,235.81
6.1 Filing CHB Walls (Exterior, Interior)
150 sqm (ext), 89.04 sqm (int)
₱417,886.48 Actual: 100.00%
Billing: 8.00%
Billing Amount: ₱417,886.48
6.2 Reinforcing CHB Walls (Exterior, Interior)
Based on wall area
₱104,471.62 Actual: 100.00%
Billing: 1.50%
Billing Amount: ₱104,471.62
6.3 Exterior Finishes (Plastering, Painting, Cladding)
202.06 sqm (ext), 178.08 sqm (int)
₱208,943.24 Actual: 100.00%
Billing: 4.00%
Billing Amount: ₱208,943.24
6.4 Interior Finishes (Partition Walls, Ceilings, Floor Finishes, Wall Finishes)
Refer to design
₱156,707.43 Actual: 100.00%
Billing: 3.00%
Billing Amount: ₱156,707.43
6.5 Doors and Windows Installation
Refer to sizes and quantity
₱104,471.62 Actual: 100.00%
Billing: 2.00%
Billing Amount: ₱104,471.62
6.6 Waterproofing Works
Refer to structural plan
₱52,235.81 Actual: 100.00%
Billing: 1.00%
Billing Amount: ₱52,235.81
7.1 Water Supply Lines (PVC 4” Pipes)
Qty: 105.66, Unit: m
₱99,248.04 Actual: 100.00%
Billing: 1.90%
Billing Amount: ₱99,248.04
7.2 Drainage (PVC 3” Pipes)
Qty: 38.64, Unit: m
₱57,459.39 Actual: 100.00%
Billing: 1.10%
Billing Amount: ₱57,459.39
7.3 Sewerage System
Qty: 1, Unit: lot
₱41,788.65 Actual: 100.00%
Billing: 0.80%
Billing Amount: ₱41,788.65
7.4 Concrete Gutter Lines
Qty: 74.53, Unit: m
₱62,682.97 Actual: 100.00%
Billing: 1.20%
Billing Amount: ₱62,682.97
8.1 Electrical Wiring and Conduits
Required based on layout
₱48,971.07 Actual: 100.00%
Billing: 0.94%
Billing Amount: ₱48,971.07
8.2 Lighting Fixtures
15-20 per unit
₱32,647.38 Actual: 100.00%
Billing: 0.62%
Billing Amount: ₱32,647.38
8.3 Power Outlets and Switches
10-15 per unit
₱24,485.54 Actual: 100.00%
Billing: 0.47%
Billing Amount: ₱24,485.54
8.4 Main Distribution Panels
Qty: 1, Unit: pcs
₱16,323.69 Actual: 100.00%
Billing: 0.31%
Billing Amount: ₱16,323.69
8.5 Emergency Lighting and Exit Signs
Refer to design
₱8,161.85 Actual: 100.00%
Billing: 0.16%
Billing Amount: ₱8,161.85
9.1 Ventilation Works
Refer to requirements
₱36,565.07 Actual: 100.00%
Billing: 0.70%
Billing Amount: ₱36,565.07
9.2 Aircon Outlet (Preparation)
Refer to requirements
₱15,670.74 Actual: 100.00%
Billing: 0.30%
Billing Amount: ₱15,670.74

Our Location

Address

Block 7, Cambridge Subdivision, Harvard St, Xavier St, Cagayan de Oro, 9000 Misamis Oriental

Contact Us

Here\'s how you can contact us for any questions or concerns.

First Name
Last Name
Email
Message
The form has been submitted successfully!
There has been some error while submitting the form. Please verify all form fields again.

JMG CONSTRUCTION & GENERAL MERCHANDISE

Phone

+63-999-619-6855 (Smart Phone), +6388-880-9757 (PLDT Landline)

EMAIL

teamjmg@googlegroups.com

Scroll to Top