2 Storey Duplex First Billing

🏡 Demolition and Building Construction of 2-Storey Duplex Residential

Client: Rifon N. Quiblat / Evelyn C. Quiblat

Location: Block 9, Lot 5, Gold City Village, Lower Balulang, Cagayan de Oro City

Item No. / Description / Qty / UnitContract Amount (₱)Actual (%) / Billing (%) / Billing Amount (₱)
1.1 Demolition
Qty: 1, Unit: lot
₱380,517.00 Actual: 85.00%
Billing: 6.19%
Billing Amount: ₱323,439.45
1.2 Mobilization
Qty: 1, Unit: lot
₱62,682.67 Actual: 90.00%
Billing: 1.08%
Billing Amount: ₱56,414.40
1.3 Permits and Licenses
Qty: 1, Unit: lot
₱7,835.37 Actual: 100.00%
Billing: 0.15%
Billing Amount: ₱7,835.37
1.4 Site Security and Safety
Qty: 1, Unit: lot
₱5,745.94 Actual: 100.00%
Billing: 0.11%
Billing Amount: ₱5,745.94
1.5 Temporary Facilities
Qty: 1, Unit: lot
₱31,341.49 Actual: 90.00%
Billing: 0.54%
Billing Amount: ₱28,207.34
1.6 Site Clearing and Preparation
Qty: 1, Unit: lot
₱94,024.46 Actual: 70.00%
Billing: 1.26%
Billing Amount: ₱65,817.12
2.1 Excavation and Earthworks
Qty: 34.92, Unit: cum
₱48,522.94 Actual: 75.00%
Billing: 0.70%
Billing Amount: ₱36,392.21
2.2 Site Grading
Qty: 300, Unit: sqm
₱416,863.77 Actual: 70.00%
Billing: 5.59%
Billing Amount: ₱291,804.64
2.3 Excavation for Foundations
Qty: 24.12, Unit: cum
₱33,515.85 Actual: 70.00%
Billing: 0.45%
Billing Amount: ₱23,461.09
2.4 Backfilling and Compaction
Qty: 16.88, Unit: cum
₱23,455.54 Actual: 20.00%
Billing: 0.09%
Billing Amount: ₱4,691.11
3.1 Concrete Footings
Qty: 9.45, Unit: cum
₱203,719.66 Actual: 100.00%
Billing: 3.90%
Billing Amount: ₱203,719.66
3.2 Reinforcement Works
Refer to structural design
₱156,707.43 Actual: 100.00%
Billing: 3.00%
Billing Amount: ₱156,707.43
4.1 Concrete Columns, Tie Beams, Slab, Stairs
Based on components
₱540,912.26 Actual: 65.00%
Billing: 6.73%
Billing Amount: ₱351,592.97
4.2 Form Works (Columns, Beams, Slab, Stairs)
Based on structural area
₱169,035.08 Actual: 100.00%
Billing: 3.24%
Billing Amount: ₱169,035.08
5.1 Scaffolding Works (Columns)
Refer to lumber requirements
₱52,235.81 Actual: 100.00%
Billing: 1.00%
Billing Amount: ₱52,235.81
5.2 Scaffolding Works (Beams)
Refer to lumber requirements
₱25,595.55 Actual: 100.00%
Billing: 0.49%
Billing Amount: ₱25,595.55
5.3 Scaffolding Works (Slab)
Refer to lumber requirements
₱26,640.26 Actual: 100.00%
Billing: 0.51%
Billing Amount: ₱26,640.26
5.4 Scaffolding Works (Stairs)
Refer to lumber requirements
₱52,235.81 Actual: 100.00%
Billing: 1.00%
Billing Amount: ₱52,235.81
6.1 Filing CHB Walls (Exterior, Interior)
150 sqm (ext), 89.04 sqm (int)
₱417,886.48 Actual: 100.00%
Billing: 8.00%
Billing Amount: ₱417,886.48
6.2 Reinforcing CHB Walls (Exterior, Interior)
Based on wall area
₱104,471.62 Actual: 100.00%
Billing: 1.50%
Billing Amount: ₱104,471.62
6.3 Exterior Finishes (Plastering, Painting, Cladding)
202.06 sqm (ext), 178.08 sqm (int)
₱208,943.24 Actual: 100.00%
Billing: 4.00%
Billing Amount: ₱208,943.24
6.4 Interior Finishes (Partition Walls, Ceilings, Floor Finishes, Wall Finishes)
Refer to design
₱156,707.43 Actual: 100.00%
Billing: 3.00%
Billing Amount: ₱156,707.43
6.5 Doors and Windows Installation
Refer to sizes and quantity
₱104,471.62 Actual: 100.00%
Billing: 2.00%
Billing Amount: ₱104,471.62
6.6 Waterproofing Works
Refer to structural plan
₱52,235.81 Actual: 100.00%
Billing: 1.00%
Billing Amount: ₱52,235.81
7.1 Water Supply Lines (PVC 4” Pipes)
Qty: 105.66, Unit: m
₱99,248.04 Actual: 100.00%
Billing: 1.90%
Billing Amount: ₱99,248.04
7.2 Drainage (PVC 3” Pipes)
Qty: 38.64, Unit: m
₱57,459.39 Actual: 100.00%
Billing: 1.10%
Billing Amount: ₱57,459.39
7.3 Sewerage System
Qty: 1, Unit: lot
₱41,788.65 Actual: 100.00%
Billing: 0.80%
Billing Amount: ₱41,788.65
7.4 Concrete Gutter Lines
Qty: 74.53, Unit: m
₱62,682.97 Actual: 100.00%
Billing: 1.20%
Billing Amount: ₱62,682.97
8.1 Electrical Wiring and Conduits
Required based on layout
₱48,971.07 Actual: 100.00%
Billing: 0.94%
Billing Amount: ₱48,971.07
8.2 Lighting Fixtures
15-20 per unit
₱32,647.38 Actual: 100.00%
Billing: 0.62%
Billing Amount: ₱32,647.38
8.3 Power Outlets and Switches
10-15 per unit
₱24,485.54 Actual: 100.00%
Billing: 0.47%
Billing Amount: ₱24,485.54
8.4 Main Distribution Panels
Qty: 1, Unit: pcs
₱16,323.69 Actual: 100.00%
Billing: 0.31%
Billing Amount: ₱16,323.69
8.5 Emergency Lighting and Exit Signs
Refer to design
₱8,161.85 Actual: 100.00%
Billing: 0.16%
Billing Amount: ₱8,161.85
9.1 Ventilation Works
Refer to requirements
₱36,565.07 Actual: 100.00%
Billing: 0.70%
Billing Amount: ₱36,565.07
9.2 Aircon Outlet (Preparation)
Refer to requirements
₱15,670.74 Actual: 100.00%
Billing: 0.30%
Billing Amount: ₱15,670.74
Scroll to Top