Revised Quotation for 2-Storey House Construction Using Hollow Blocks/Bricks
Client: Michael Dan Santiago
Location: Gingoog City
Date: Oct 20, 2024
I. Project Overview
- Project Description: Construction of a 3×6 meter, 2-storey house (L-Type House) using hollow blocks or bricks instead of containers. The project includes concrete foundations, brick or hollow block walls, and traditional roofing.
II. Scope of Work
- Site Preparation and Foundations
- Ground clearing and grading.
- Foundation setup (concrete slab for brick/block structure support).
- Structural Work
- Construction using hollow blocks or bricks for both floors.
- Reinforcement of walls with columns and beams.
- Installation of exterior stairs and roof deck.
- Interior Work
- Installation of glass sliding doors (ground floor).
- Installation of steel doors.
- Electrical and plumbing installations (kitchen, bathroom, and lighting).
- Exterior and Roofing
- Roofing installation over the second-floor deck.
- Minor landscaping (optional, as per client’s request).
- Final Finishing and Inspection
- Painting, sealing, and ensuring all utilities are operational.
- Final inspection for compliance with building codes.
III. Cost Breakdown
| Item Description | Qty | Unit Price (PHP) | Total (PHP) |
|---|---|---|---|
| 1. Site Preparation | |||
| Clearing and grading | 1 lot | 15,000 | 15,000 |
| Foundation (concrete slab) | 1 lot | 35,000 | 35,000 |
| 2. Hollow Blocks/Brick Structure | |||
| Hollow blocks (6″ thick) | 500 pcs | 35/block | 17,500 |
| Cement | 100 bags | 300/bag | 30,000 |
| Sand and gravel | 1 lot | 25,000 | 25,000 |
| Reinforcement steel bars (12mm) | 500 kg | 55/kg | 27,500 |
| Brick or block laying labor | 1 lot | 50,000 | 50,000 |
| Columns and beams | 1 lot | 45,000 | 45,000 |
| Exterior stairs and handrails | 1 lot | 45,000 | 45,000 |
| Roof deck construction | 1 lot | 65,000 | 65,000 |
| 3. Roofing and Finishes | |||
| Metal roofing sheets (deck cover) | 30 sqm | 500/sqm | 15,000 |
| 4. Interior Work | |||
| Electrical system | 1 lot | 40,000 | 40,000 |
| Plumbing system | 1 lot | 30,000 | 30,000 |
| Glass sliding door (ground floor) | 1 unit | 25,000 | 25,000 |
| Steel door | 2 units | 10,000/unit | 20,000 |
| Interior finishing (walls, ceiling) | 36 sqm | 800/sqm | 28,800 |
| Flooring (vinyl or tile options) | 36 sqm | 1,200/sqm | 43,200 |
| 5. Labor and Miscellaneous | |||
| Labor (skilled workers) | 1 lot | 150,000 | 150,000 |
| Transportation of materials | 1 lot | 30,000 | 30,000 |
| Miscellaneous expenses (permits, etc.) | 1 lot | 20,000 | 20,000 |
| Total Estimated Cost | | | 786,000 PHP |
IV. Additional Considerations
- Timeline: The project is estimated to take around 2 to 3 months for completion, depending on weather conditions and material availability.
- Payment Terms:
- 30% upon contract signing for procurement of materials and initial site work.
- 30% midway through construction (after completion of structural work).
- 40% upon project completion and final inspection.
V. Exclusions
- Landscaping beyond the basic open area.
- Additional furnishings (e.g., kitchen cabinetry, built-in closets).
- Any additional requests or changes to the design during construction may affect the final cost.
VI. Contact Details
- Company Name: JMG Construction & General Merchandise
- Email: teamjmg@googlegroups.com
- Mobile: 09996196855
- Office Address: Cambridge Subdivision, Harvard St Block 7 Lot 32, Cagayan de Oro, 9000 Misamis Oriental.